Labor Productivity Calculator

Calculate labor productivity (output per labor hour), productivity index, and unit labor cost to measure workforce efficiency.

Formulas Used

Labor Productivity

Labor Productivity = Total Output ÷ Total Labor Hours

Total Labor Hours = Number of Workers × Hours Worked per Worker

Output per Worker

Output per Worker = Total Output ÷ Number of Workers

Unit Labor Cost (ULC) — requires wage rate:

Total Labor Cost = Hourly Wage Rate × Total Labor Hours

Unit Labor Cost = Total Labor Cost ÷ Total Output

Productivity Index — requires baseline productivity:

Productivity Index (%) = (Labor Productivity ÷ Baseline Productivity) × 100

A value above 100% means the workforce is outperforming the baseline standard.

Assumptions & References

  • Labor productivity is measured as partial factor productivity — output relative to labor input only; it does not account for capital, materials, or technology inputs.
  • Formula reference: U.S. Bureau of Labor Statistics (BLS) — Productivity & Costs methodology; OECD Manual on Productivity Measurement (2001).